International Code of Practice (INTCOP 7.1)
Perimeter Fence Compliance › INTCOP 7.1
Effective 24 February 2020. Supersedes all previous versions.
Installations commissioned after 24 February 2020, and new additions made after that date to existing installations, must comply with INTCOP 7.1 to be certified by Gallagher. The Code of Practice outlines the minimum acceptable standard for Gallagher certification of an energized security fence. It is applied via an on-site system inspection and documentation review by Gallagher together with the Channel Partner, covering safety and application of product and workmanship practices, but not compliance to any other regulation, code, standard, construction, or specification of the installation.
📄 Source document: 3E0654 - Gallagher International Code of Practice, Perimeter Systems (PDF). The governing per-market fence-installation standards (AS/NZS 3016, BS1722-17, SANS10222-3, GB/T 7946, EN60335-2-76, IEC60335-2-76) are listed in Standards by Market. Compliance of the installation to any such standard is the responsibility of the Channel Partner.
Certification
Required annually for Gallagher certification to remain valid
Inspection by an authorised Gallagher staff member
Grades A (excellent) through E (failure: major remedial work required, safety error)
Grade D or E means remedial work required before the certificate is issued
Signed: Greg Barclay, Chief Operating Officer, Gallagher NZ HQ.
Prohibited Configurations
Energised barbed wire or razor wire
Mantrap construction (one that can entrap or tangle a person, preventing them from withdrawing from repeated shocks)
Multiple energisers on the same fence wire (single energiser per circuit only)
Installation in a combustible or hazardous atmosphere (definition of hazardous areas is the responsibility of the site H&S authority)
Connecting Leads (Lead-Out Cables)
Leads run inside buildings shall be insulated from earthed structural parts using insulated HV cable
Leads shall not share conduit with mains supply, communication, or data cables
Leads and fence wires shall not cross above overhead power or communication lines
All mains-operated ancillary equipment connected to the fence circuit must provide isolation between the fence circuit and the supply mains equivalent to the energiser
Personnel Access and Gates
Fence conductors should not be energised unless authorised persons have been informed of the fence function
Gates shall be capable of being secured and opened without the operator receiving a pulse
Where a gate is used for personnel access, a method to de-energise conductors should be included to prevent inadvertent contact
Maintenance and Certification
Every installation shall have a maintenance program offered to the System User
The program should be documented, take into account environmental issues at the site, and keep the installation compliant with INTCOP 7.1 and the product documentation
Certification is performed by an authorised Gallagher staff member only, using the Commissioning Document Set (3E2391)
The certificate is issued in the user's name with site address and date
Annual re-certification is required to maintain certification
If there is a conflict, the requirements in INTCOP are supplementary to country-of-installation standards and should be considered Manufacturer's Minimum Installation Criteria.