Commissioning Checklist Summary
Perimeter Fence Compliance › Commissioning Checklist Summary
Source document: 3E2391 v2.2, Commissioning Document Set: Perimeter Security Monitored Pulse Fencing. Reference documents: International Code of Practice (INTCOP 7.1) (3E0654) · Technical Reference Manual (3E0901) · Local standards, as applicable.
This document set must be completed by the Gallagher Certified Channel Partner before any site is handed over to the end user. A Gallagher representative must verify and countersign the System Commission Sheet. Certification is only granted once all inspections pass and remedial work is addressed.
Purpose
The commissioning document set provides the Channel Partner and System User with a reference to confirm compliance with the Gallagher International Code of Practice (INTCOP 7.1) (3E0654) and Gallagher installation standards at the time of commissioning and handover.
The document set consists of three sections that can be separated as required:
1
Certification Inspection Criteria
Reference for Gallagher representative
2
Certification Inspection Checklist
Completed by Gallagher representative during inspection
3
System Commission Sheet and Testing Schedule
Completed by Channel Partner; verified by Gallagher representative
Pre-Commissioning Requirements
The following must be in place before the Gallagher certification inspection is booked:
Section 1 - Certification Inspection Criteria
This section defines each checkpoint in the Certification Inspection Checklist. Work through each area before requesting the Gallagher inspection.
1. Safety
1.1 Code of Practice
Installation meets Gallagher Code of Practice minimum standard
Ancillary equipment is compatible with Gallagher equipment
Only Gallagher supplied and/or approved product is used
Prevention of inadvertent public contact is installed
Installation is not within a hazardous area
1.2 Warning Signs
Fitted at maximum 10 m (30 ft) spacing along the entire fence line
Fitted at every gate, every change of direction, and on site noticeboards
Visible from both sides of the fence and from the public access area
Securely mounted close to a support post (not free to move in wind)
1.3 Hostile Toppings
Any razor wire, barbed wire, or hostile topping is at least 1 m (3 ft 4 in) away from the pulse fence (to prevent simultaneous contact)
Hostile toppings are not electrified
1.4 Entrapment Points
No mantraps or entrapment points exist
Distances between pulse fencing and other structures are compliant with Gallagher installation standards
2. Fence Line Inspection
2.1 Physical Barrier (Host Fence)
Minimum height 1.5 m (5 ft)
Provides public protection from the pulse fence
Fence fabric is sound, posts upright, fence line straight between strain posts
Fence is not attached to overhead power-line support structures
2.2 Quality of Fence Manufacture
All welded joints cleaned and coated correctly
Metallic structures and components are compatible materials
Components are suitable for the installation environment and protected from corrosion
2.3 Intermediate Post Fitting
Posts mounted correctly with all fixings secure
Minimum 3 fixings per post over 2.4 m (7 ft 10 in) high
No vertical or horizontal deflections exceeding allowable limits
Maximum post spacing: 4 m (13 ft)
Pulse fence extends minimum 600 mm (24 in) above the physical fence barrier
2.4 Strain Post Fitting
Posts stable and fit for purpose
Strain posts do not protrude above the Gallagher security post
Installed at every change of zone and change of direction
Bracing does not compromise perimeter security or create entrapment
2.5 Vegetation and Debris
Vegetation cleared at least 1 m (3 ft 4 in) from the fence in both directions
All scrap and construction debris removed from the fence line before energising
2.6 Level of Security
Locations where the pulse fence does not protect the perimeter have been identified and acknowledged by the site operator/owner
Installation meets the security requirements of the site
3. Fence Wire and Insulation
3.1 Insulators
Strain insulators fitted correctly
Intermediate insulators fitted correctly; pins secure; break-away claws used correctly
Energised fence wires fitted correctly in insulators
Gallagher tensioners installed correctly using Gallagher approved mounting techniques
Wire secure around centre spindle; pawl locked in correct position
3.2 Fence Wire Installation
Pulse fence wire and insulated HV cable is Gallagher supplied
Minimum spacing between adjacent wires: 50 mm (2 in)
All wires tensioned evenly, maintains geometry, deflects under attack, no sag under normal conditions
Wire tensioning devices accessible for maintenance
All wire joints clamped securely using Gallagher approved methods
3.3 Separation Distances
Clearance between pulsed conductors and physical barrier, buildings, other fence circuits is compliant
Distance between energised fence wires and power or communications lines is compliant
Any fence wire closer than 30 mm (1-3/16 in) to any object has insulation applied
Cable insulation is sturdy, continuous, uncut, rated for HV voltages (over 10 kV), and securely clamped
4. Gates
4.1 Installation of Gates
Gate posts and leaves are upright in open and closed positions
Bottom wire maximum 125 mm (4-7/8 in) from ground level
Quality of welds and final coatings checked
All gaps maximum 50 mm (1-15/16 in) or protected with anti-climb provisions (including hinge points, latch points, abutments)
Locking devices operate effectively
Gate geometry maintained after pulse fence installation
4.2 Gate Safety and Detection
All gate leaves bonded to fence structure earth
Gates can be opened and locked without touching energised fence wires
Gate switch(es) installed correctly to Gallagher specification (mounting brackets, mechanical stop, drip loops, moisture ingress protection, earth bolt, distances between parts)
Earth bolt used correctly and making good contact
Gate switch placement is not a hazard; mechanical protection is in place
Gate switch functions within 50 mm (1-15/16 in) of opening and alarm annunciation confirmed
4.3 Gate Configuration and Fence Interface
Distances between gate and pulse fence are compliant
Gate hinges, wheels, drop rods, support structures are protected against tampering and scaling
Pulse fence configuring does not clash when gates are operated
No climbing point created by height differences between fence and gate
Gate feed wire coils are fit for purpose, will not snag during gate operation, not accessible from public area, not too close to ground
5. Configuring
5.1 Configuring Functionality and Appearance
Wire configurations are tidy, straight, bends consistent, wires even length
Configurations are straight and vertically aligned
Configuring is complete on energised and earth wires, minimum 30 mm (1-3/16 in) from other wires or fence structure
Top wire is an energised wire (unless under overhead power lines)
No 2 adjacent earth wires; no 3 adjacent energised wires of the same circuit
5.2 Anti-Climb Protection
Physical barrier is shorter than pulse fence unless protected by anti-climb provisions
Anti-climb configuring protects tensioners
Gaps in pulse fence minimised to detect or prevent intrusion
Anti-climb applied at strain positions, junctions, and gateways
Wherever possible, 4 or more wires used for anti-climb, connected in series
Anti-climb wires sufficiently supported to minimise damage and maintenance
Associated structures near fence line (lamp posts, camera poles) suitably protected from climbing
5.3 Anti-Intrusion Protection
Anti-burrow (anti-dig) construction is fit for purpose and does not clash with pulse fencing
Bottom fence wire: maximum 125 mm (4-7/8 in) from ground, minimum 30 mm (1-3/16 in) clearance from metal parts of the fence
6. Controllers and Associated Equipment
6.1 Controller Mounting and Protection
Equipment located in a suitable place, not influenced by environment, vandalism, or wildlife
Equipment safely accessible for service and maintenance
Controllers mounted square, level, and secured
All cabling suitably contained and routed tidily
Fence feed cables securely contained and terminated into controllers
Distance between fence HV cables and low voltage cabling is compliant
0 V (DC negative, GND) is common between devices
6.2 Synchronisation
System is synchronised site-wide and locally at field cabinets
Synchronising settings correct on every controller
Where synchronisation cannot be achieved, non-sync circuits are separated by physical barrier or sufficient distance
6.3 Auxiliary Equipment
Auxiliary equipment installed appropriately with correct isolation distances from HV cabling
All cabling suitably mounted, routed, and terminated (ferrules, terminal blocks)
7. Earthing and Lightning Protection
7.1 Earthing of Structures
Exposed metallic parts of physical barrier fence and pulse fence supports are earthed
Metallic structures (buildings, rooftops) effectively earthed; if a separate system, pulse fence earth is independent
All strain posts bonded to pulse fence earth wires
All gate posts bonded to pulse fence earth wires
All gate leaves bonded to pulse fence earth wires
Earthing is continuous under gates where necessary
7.2 Earthing of Equipment
Electric fence earth continuity is fit for purpose
Multiple fence controller earths are bonded together
Minimum earthing requirements for fence controller are met, installed in a secure location, connected correctly
Additional earth rods installed if poor earth continuity
Minimum 2 m (6 ft 7 in) maintained between pulse fence earth and all other earthing systems
Where an earthing mat system is in use, pulse fence is connected directly to it and does NOT use a separate earth (authority for connection may be required)
7.3 Lightning Protection
Lightning earth system installed correctly in an appropriate secure location
Lightning earth stakes at least 10 m (33 ft) from the fence earth and any other earth system
Lightning diverters adjusted correctly
Earth side of lightning diverters is NOT directly connected to fence earth or associated structures
8. Cabling
8.1 Fence Feed (Lead-out) Cables
Fence feed cables mechanically protected (conduit, ducting) or located to minimise damage and tampering
Conduit/ducting brought as close as practical to termination joints (HV cable to fence)
Feed cable terminations clamped appropriately; cable stress relieved through insulators or cable ties
Connection of feed cabling is at a strain position, not mid-span
Appropriate jointing sealant used where necessary
Only Gallagher HV cable used for fence feed cables
8.2 Underground Cabling and Ducting
Ducting is fit for purpose, positioned locally to fence controllers and equipment
No other cables (other services) installed in lead-out ducting; minimum separation maintained
Ducting sealed against weather and vermin; suitably secured
9. Commissioning
9.1 System Power and Communications Established
Mains power control is adjacent to controllers; power is established
Backup batteries installed and connected
Any associated UPS systems identified and established
Communications between controllers and associated equipment is established
9.2 System Performance
Testing outlined in the System Commission Sheet and Testing Schedule has been completed
System performs as required
System can be armed and disarmed using designated control methods
After arming, there are no standing alarms associated with the system
9.3 System Alarm Testing
All fence zones generate alarm with short circuit and open circuit (where possible)
All gates, when opened, generate the necessary alarms
All gate fence circuits generate alarm with short circuit and open circuit (where possible)
Any interface with third party equipment activates correctly when alarms are generated
9.4 User Interfaces
Any PC or keypad is in an appropriate environment with access available for service and maintenance
User Interface on the front end of the system is relevant and informative
9.5 Operator Training
Operator training has occurred; end user is confident and competent
Arm/disarm process confirmed understood
Alarm identification and processing confirmed understood
Basic fault finding and product identification confirmed understood
All personnel on site have been informed of the energised fence and associated shock hazards
10. Maintenance
10.1 Maintenance Program
A maintenance program has been defined for the installation
Contamination has been considered
Battery replacement has been considered
Cleaning, vegetation control, and trash removal have been considered
Emergency repair provisions are in place (spare product or service call-out process)
Section 2 - Certification Inspection Checklist
Grading Scale
A
Excellent
B
Good
C
Fair
D
Failure, minor remedial work required (functional error)
E
Failure, major remedial work required (safety error)
Any D or E grade must be addressed and initialled by both the Gallagher representative and the installer before certification is granted.
Installation Details (to be recorded at time of inspection)
Site Details
Site Name:
Site Address:
Contact Personnel:
Phone / Email:
Channel Partner (Installer) Details
Company Name:
Company Address:
Contact Personnel:
Phone / Email:
Description of System
Security Fence type (F3x / F4x / F22 / other)
Fence topping type
Fence height
Pulse fence height
Fence length
Number of controllers
Number of zones
Number of cabinets
Other monitoring
Inspection Checklist
Safety
1.1 Code of Practice
1.2 Warning Signs
1.3 Hostile Toppings
1.4 Entrapment Points
Fence Line
2.1 Physical Barrier
2.2 Quality of Manufacture
2.3 Intermediate Post Fitting
2.4 Strain Post Fitting
2.5 Vegetation and Debris
2.6 Level of Security
Wire & Insulation
3.1 Insulators
3.2 Fence Wire Installation
3.3 Separation Distances
Gates
4.1 Installation of Gates
4.2 Gate Safety and Detection
4.3 Gate Configuration & Fence Interface
Configuring
5.1 Functionality and Appearance
5.2 Anti-Climb Protection
5.3 Anti-Intrusion Protection
Controllers
6.1 Mounting and Protection
6.2 Synchronisation
6.3 Auxiliary Equipment
Earthing & Lightning
7.1 Earthing of Structures
7.2 Earthing of Equipment
7.3 Lightning Protection
Cabling
8.1 Fence Feed Cables
8.2 Underground Cabling & Ducting
Commissioning
9.1 Power & Comms Established
9.2 System Performance
9.3 System Alarm Testing
9.4 User Interfaces
9.5 Operator Training
Maintenance
10.1 Maintenance Program
Confirmation of Compliance
A Gallagher employee must confirm that this checklist attests that the site is compliant with the Gallagher Code of Practice and that the installation is of sufficient standard to be signed over to the user. Any remedial work must be addressed and initialled by both the Gallagher representative and the installer.
Site Name
Inspector's Name
Signature
Date
Section 3 - System Commission Sheet and Testing Schedule
This section is completed by the Gallagher Certified Channel Partner. The Gallagher representative uses it to verify and certify the installation. Each check item has two tick boxes, the first is for the Channel Partner, the second for the Gallagher representative. Both parties should initial each box.
Site and Installer Details
Site Name
Site Address
Contact Personnel
Phone / Email
CP Company Name
CP Company Address
CP Contact
CP Phone / Email
Physical Checks
Control Equipment
System configuration (tick applicable):
Controller Serial Numbers:
1
2
3
4
Method of Monitoring:
Expected number of users: ___________
Protection of Equipment
Fence Circuit Physical Parameters
1
2
3
4
5
6
7
8
System Settings (record per controller)
Pulse Timing (seconds) SLOW
Pulse Rate SLOW
Alarm Pulse Count
Alarm Reset Time
Entry Delay
Exit Delay
Pulse Interval (s)
Battery Voltage STOP
Battery Voltage SLOW
Fence Warning (kV)
Fence Alarm (kV)
Lightning Protection
I/O Functionality
Fence Circuit Electrical Parameters
1
2
3
4
5
6
7
8
Fence Alarm Functionality
All results must indicate correct zone identification.
1
2
3
4
5
6
7
8
Fence Controller Internal Voltage Tests
1
2
3
4
Controller System Alarms
1
2
3
4
Software Information
Software Version
License Number
License Expiry
Additional Documents (Attachments)
Wiring Diagrams
Fence Configuration Diagrams
Maintenance Program
Perimeter Layout Diagram
The perimeter layout diagram must include: dimensions, sub-assembly types and quantities, controllers, earthing systems, zones, cable routes, conduit, underground ducting.
Testing Completion Declaration
Confirmation of Testing
I/We confirm that all tests and checks detailed in this document have been undertaken in accordance with the Gallagher Code of Practice and relevant installation standards, and that the system is ready for inspection by a Gallagher representative.
Print Name
Signature
Company
Date
Who Performs Commissioning
System Commission Sheet and Testing Schedule
Gallagher Certified Channel Partner
Certification Inspection Checklist
Gallagher representative (with CP in attendance)
Final sign-off and certification
Gallagher representative
User training
Gallagher Certified Channel Partner
Certification is a mandatory requirement at the end of every new installation. The Gallagher representative must verify the System Commission Sheet before certification is granted.
🔗 Related
Source: 3E2391 v2.2, INTCOP
Last updated
Was this helpful?